Which of the following is not an option to achieve reliable cost and effort estimate?

To achieve reliable cost and effort estimates, a number of options arise:1.Delay estimation until late in the project [since, we can achieve 100%accurate estimates after the project is complete!]2.Base estimates on similar projects that have already been completed.3.Use relatively simple decomposition techniques to generate project costand effort estimates.4. Use one or more empirical models for software cost and effortestimation.Unfortunately, the first option, however attractive, is not practical. Cost estimatesmust be provided “Up front”. However, we should recognize that the longer wewait, the more we know, and the more we know, the less likely we are to makeserious errors in our estimates.The second option can work reasonably well, if the current project is quitesimilar to past efforts and other project influences [e.g., the customer, businessconditions, the SEE, deadlines] are equivalent. Unfortunately past experience hasnot always been a good indicator of future results.The remaining options are viable approaches the software project estimation.Ideally, the techniques noted for each option be applied in tandem; each used ascross check for the other.Decomposition techniquestake a “divide and conquer”approach to software project estimation. By decomposing a project into majorfunctions and related software engineering activities, cost and effort estimation canbe performed in the stepwise fashion.Empirical estimationmodels can be used to complement decompositiontechniques and offer a potentially valuable estimation approach in their own right. Amodel based on experience [historical data] and takes the form

We have textbook solutions for you!

The document you are viewing contains questions related to this textbook.

Chemistry: The Molecular Science

Moore/Stanitski

Expert Verified

D = f [vi]Where d is one of a number of estimated values [e.g., effort, cost, projectduration and we are selected independent parameters [e.g., estimated LOC [line ofcode]].Each of the viable softwarecost estimationoptions is only as good as thehistorical data used to seed the estimate. If no historical data exist, costing rests on avery shaky foundation.

Chapter 4Project Monitoring System

4.1 PERT ChartProgram evaluation and review technique [PERT] and critical path method[CPM] are two project scheduling methods that can be applied to softwaredevelopment. These techniques are driven by following information:Estimates of EffortA decomposition of the product functionThe selection of the appropriate process model and task setDecomposition of tasksPERT chart for this application software is illustrated in figure 3.1. The criticalPath for this Project is Design, Code generation and Integration and testing.Aug-2008Figure 4.1 PERTcharts for “University Study CenterManagement SystemManagement System”.4.2 Gantt ChartGantt chart which is also known as Timeline chart contains the informationlike effort, duration, start date, completion date for each task. A timeline chart canbe developed for the entire project.

Upload your study docs or become a

Course Hero member to access this document

Upload your study docs or become a

Course Hero member to access this document

Which of the following is not an option to achieve reliable cost and effort estimate?

Base estimates on similar projects that have already been completed

Use one or more empirical models for software cost and effort estimation

Use relatively simple decomposition techniques to generate project cost and effort estimates

The ability to translate the size estimate into human effort, calendar time, and dollars

Answer : D

Sponsored Ad

अगर आप कम्पटीशन एग्जाम की ऑनलाइन तैयारी कर रहे है तो यहाँ से आप फ्री में Online Test

View More Related Question

1] Which of the following process is concerned with analyzing the costs and benefits of proposed changes?

Change management

Version management

System building

Release management

View Answer

2] Which of the following risks are derived from the organizational environment where the software is being developed?

People risks

Technology risks

Estimation risks

Organizational risks

View Answer

3] Which of the following process ensures that versions of systems and components are recorded and maintained?

Codeline

Configuration control

Version

Workspace

View Answer

4] Which one is not a size measure for software product?

LOC

Halstead’s program length

Function Count

Cyclomatic Complexity

View Answer

5] Which version of COCOMO states that once requirements have been stabilized, the basic software architecture has been established?

Early design stage model

Post-architecture-stage model

Application composition model

All of the mentioned

View Answer

Which of the following is not included in the total effort cost *?

Q.
Which of the following costs is not part of the total effort cost?
B.
costs of providing heating and lighting office space
C.
costs of lunch time food
D.
costs of support staff
Answer» c. costs of lunch time food
Which of the following costs is not part of the total effort cost? - McqMatemcqmate.com › discussion › which-of-the-following-costs-is-not-part-of-th...null

Which of the following is an important factor that can affect the accuracy and efficacy?

Explanation: As size increases, the interdependence among various elements of the software grows rapidly.

What is not an approach to software cost estimation?

1 Answer. For explanation: Critical is no such standard approach of cost estimation.

Which of the following is not considered as a risk in project management Mcq?

Which of the following is not considered as a risk in project management? Explanation: Testing is a part of project, thus it can't be categorized as risk.

Chủ Đề